TOC TIEN WATER TREATMENT PLANT PHASE 2 – 50.000 M3/DAY

PROJECT: DESIGN, CONSTRUCTION, SUPPLY, AND INSTALLATION OF TECHNOLOGICAL EQUIPMENT AND SCADA CONTROL SYSTEM

  • Investor: Hai Chau Vietnam Company Limited
  • Status: New construction
  • Capacity: 50 MLD
  • Completion: 6/2023
  • Scope of work: Design, construction, supply, and installation of technological equipment and SCADA control system for Toc Tien 2 Water Plant Phase 1 in the form of EPC Turnkey.

The project includes:

  1. Raw water pumping station, capacity 150,000 m3/day;
  2. Raw water pipeline, HDPE Ø1000, L = 12 km;
  3. Flow distribution tank;
  4. Water treatment facilities, capacity 50,000 m3/day;
  5. Reservoir, A1: 3,000 m3 and A2: 4,500 m3;
  6. Clean water pumping station, capacity 72,000 m3/day;
  7. Chemical building; Chlorination building.
  8. Sludge treatment system.

TK+ project achievements