PROJECT: DESIGNING, MANUFACTURING, PROCUREMENT, RETROFITTING, AND INSTALLATION OF ALL EQUIPMENT FOR THE EMERGENCY SLUDGE TREATMENT SYSTEM OF THU DUC WATER BOO.
- Investor: Thu Duc BOO Joint Stock Company.
- Status: New construction.
- Capacity: 300 MLD.
- Completion: 12/ 2022.
Scope of work: Designing, manufacturing, procurement, retrofitting, and installation of all equipment for the emergency sludge treatment system of Thu Duc WTP:
- Sludge thickening tank.
- Sludge conditioning tank.
- Frame filter press system.
- Automatic polymer dosing system.
- Electrical control system.